HomeBrowse ProjectsSkyline Tower — Phase 1 MEPF Fit-out
Skyline Tower — Phase 1 MEPF Fit-out
URGENTSeeking: ConsultantHVAC Design & Engineering

Skyline Tower — Phase 1 MEPF Fit-out

KarachiPosted Sep 6, 2026Deadline: Sep 10, 20261 / 20 bids · 19 spots left

Project Description

Skyline Tower — Phase 1 MEPF Fit-out

Turn-key MEPF fit-out covering design, installation coordination, testing, and commissioning.

Project Overview

An 18-storey Grade-A corporate tower with 2 basement levels and an approximate gross floor area of 480,000 sq. ft. The engagement runs from schematic design through testing and commissioning.


HVAC Scope

  • Central chilled-water plant: 2 × 350 TR water-cooled screw chillers with 30% N+1 redundancy, primary/secondary pumping, decoupled loops, and rooftop cooling towers with VFD fans.
  • Air handling: 32 VAV AHUs—typically 2 per floor and 4 per mid-rise tenant floor—with BACnet IP integration to the BMS.
  • Ductwork: Pre-insulated GI ductwork to SMACNA, VAV terminals for open-plan zones at a minimum of 1 per 750 sq. ft., and silencers on all main risers.
  • Ventilation: Dedicated outdoor air at 10% design flow with roof-MAU heat recovery providing at least 65% sensible efficiency.
  • Car-park ventilation: Basement CO monitoring and jet-fan ventilation.
  • BMS: Tridium Niagara AX with Modbus-TCP integration for chillers, pumps, and VAVs.

Electrical Scope

  • LV distribution: 2 × 1,250 kVA transformers with KE and generator ATS changeover, plus 11 kV utility HT to the primary substation.
  • Standby generation: 2 × 800 kVA prime generator sets with N+1 configuration and 24-hour fuel autonomy.
  • Distribution and containment: Main LV panels, floor-level DBs, and dedicated cable-tray routes for power, control, and ELV.
  • Lighting: DALI-controlled LED lighting, occupancy sensors on typical floors, and emergency lighting with a central battery inverter.
  • Small power: Minimum 1 duplex outlet per 60 sq. ft. based on tenant plans.
  • ELV: Dedicated rooms on every floor with access control, CCTV, IP-PA, Cat-6A cabling, and an OS2 fibre spine.

Plumbing Scope

  • Water supply: Ground tank and booster-pump set feeding a 30 m³ roof tank, with zoned cold/hot-water distribution and circulation.
  • Rainwater harvesting: 25 m³ rooftop irrigation tank.
  • Grey-water recycling: Recycled water for WC flushing from floors 2–18.
  • Sewage and waste: Gravity drainage to the basement holding tank with twin-pump ejection to the municipal main.

Fire Protection Scope

  • Sprinklers: Wet system to NFPA 13—light hazard in typical areas and ordinary hazard group 1 in basements and MEP rooms.
  • Fire hose reels: NFPA 14 system with 2 standpipes per floor.
  • Fire alarm: Addressable system with 2 loops per floor, voice evacuation, phased evacuation logic, and a roof-mounted alarm mimic.
  • Fire pumps: Electric duty, diesel standby, and jockey pumps.
  • Gaseous suppression: Inergen or Novec protection for ELV and UPS rooms.

Required Deliverables

  1. Design-freeze package covering basic and detailed design.
  2. Discipline-specific BOQ with at least 3 quotations for each package.
  3. Weekly progress reports and monthly financial reconciliation.
  4. Commissioning and TAB report before handover.
  5. Complete O&M manuals and BIM as-built model in Revit MEP 2025.

Acceptance Criteria

  • HVAC: Air balance within ±10% of design CFM in accordance with AABC.
  • Fire: 100% device functional testing and fire-marshal sign-off.
  • Electrical: Complete LV switchboard type testing and insulation-resistance records for every circuit.
  • Plumbing: 24-hour hydrostatic testing at 1.5× working pressure.

Expected Deliverable Milestones

1

Design freeze — MEPF schematics

2

Long-lead equipment ordered

3

Rough-in complete — Floors 1–6

4

Rough-in complete — Floors 7–18

Required Bid Submission Sections

Your bid must include all of the following sections to be considered.

1

admin

Required
2

experience

Required
3

tech

Required
4

financial

Required
5

timeline

Required
6

review

Required

Bids Received

1 total bids

Bid details are only visible to the project owner.

Tender Status

Bidding Closed

Submission deadline has passed

Sep 11, 2026 – Sep 28, 2026

DeadlineSep 10, 2026
Bids received1 / 20

19 spots remaining

LocationKarachi
SeekingConsultant

Bidding Closed

The submission deadline for this tender has passed. No further bids are being accepted.

About the Client

KS

Klyron Studio

Verified client
Karachi, Pakistan
Project posted on MEPFSuite
Verified company

Before You Bid

  • Ensure PEC registration is current
  • Prepare company profile document
  • Have BOQ template ready
  • List 3+ similar completed projects
  • Obtain bid security if required